Internal handoff
Responsible roles: the Account Executive signs the record · the Delivery Lead reviews it before Project Set-up is sent
Guided workspace
Find the next step, exact owner, and approved file.
Enterprise Customer Implementation
The written playbook, operational runbook, and meeting cadence — all kept in sync with this map.
Momentum AMP · Enterprise Solutions Consulting
Six phases. Seventeen stages. Four customer sign-offs and one internal handoff gate. Two to six months from signature through hypercare and formal handover.
Phase 1
Sales working the deal. We assess how hard it will be and log every promise made before signature.
Stages 0a–0c · Before signature
Phase 2
Contract signed. Sales hands off. We get set up and run the customer kickoff.
Stages 1–3 · 1–2 weeks
Phase 3
Discovery and scoping. The scope document gets signed and the dates become real.
Stages 4–5 · 2–4 weeks
Phase 4
Configuration, the final trial conversion, customer testing and sign-off, then training.
Stages 6–9 · 4–12 weeks
Phase 5
Readiness check, go/no-go, cutover, then four to six weeks of hypercare and a confirmed move to steady state.
Stages 10–11a · 4–6 weeks
Phase 6
Formal handover closes implementation within the 2–6 month journey; ongoing Customer Success, value reviews, and growth follow.
Stages 12–13 · Handover, then ongoing
Role-based view
Follow the stages from left to right. Each stage sits in the lane of the role accountable for moving it forward; customer questionnaires and sign-offs appear in their own lane.
Who owns each step?
Choose a role to highlight its work. Select any stage to open the instructions below.
G0
S0a
G0b
S0b
G0c
S0c
G1
S1
G2
S2
G3
S3
G4
S4
G5
S5
G6
S6
G7
S7
G8
S8
G9
S9
G10
S10
G11
S11
G11a
S11a
G12
S12
G13
S13
Select a stage to see owners, outputs, and the exit test
Customer questionnaire · Stage 0b Solution shaping · pre-contract
Momentum AMP Evaluate
Sent before contract by Enterprise AE. Unlocks: Proposal and contract. View details
Internal record · Stage 1 Handoff · internal handover
Momentum AMP AE Opportunity Record
Sent at contract signature, before kickoff by Nobody — internal only, never sent to the agency. Unlocks: Project Set-up is sent. View details
Customer questionnaire · Stage 2 Setup
Momentum AMP Project Set-up
Sent right after contract signature, once the AE Opportunity Record is accepted by ESC Delivery Lead. Unlocks: Discovery Workbook. View details
Customer questionnaire · Stage 4 Discovery
Momentum AMP Discovery Workbook
Sent discovery, after Project Set-up (optional pre-contract path available) by ESC Delivery Lead. Unlocks: Scope is written. View details
Gate sign-off · Stage 5 Scope Sign-off
Momentum AMP Scope Sign-off
Sent end of discovery, before build by ESC Delivery Lead. Unlocks: Build starts; change control applies. View details
Gate sign-off · Stage 7 Data Migration
Momentum AMP Data Accuracy Sign-off
Sent after the final trial conversion by Data Migration Lead. Unlocks: Final conversion is planned. View details
Gate sign-off · Stage 8 Testing
Momentum AMP Testing Sign-off
Sent when agency testing is complete by ESC Delivery Lead. Unlocks: Training and go / no-go. View details
Gate sign-off · Stage 10 Go-Live
Momentum AMP Go-Live Sign-off
Sent at the go / no-go meeting, before cutover by ESC Delivery Lead. Unlocks: Final conversion and go-live. View details
Customer Success instrument · Stage 12 Handover · Stage 13 Grow
Customer Success review
Sent at handover and each review cycle by Customer Success. Unlocks: Ongoing account reviews (not an implementation gate). View details
Not every Enterprise account needs custom work. This branch only opens when standard configuration cannot meet a requirement. It runs in parallel with the main implementation and must be signed off before go-live.
Need identified
Stage 4 · Discovery
The ESC Delivery Lead and Engineering Authority flag a requirement that standard configuration cannot satisfy.
Scoping request
Stage 4 · Discovery
Capture the business problem, expected behavior, and out-of-scope boundaries in a formal request.
Approve scope / cost
Stage 5 · Scope sign-off
Sign a Change Order or Custom Development SOW before any build begins.
Build, QA & accept
Stages 6–8
Engineering builds it, QA validates it, and the customer accepts it during UAT before go-live.
Stage 5 documents
The Custom Development SOW and Change Order live with the Stage 5 documents above — attach or update them there.
Merge-back point
Built work must pass UAT at Stage 8 before the go / no-go gate at Stage 10.
Open document libraryG1 is the signed internal AE Opportunity Record reviewed by Delivery. The customer then signs scope, data accuracy, testing, and go-live. Each gate's evidence lives with that stage's documents.
Responsible roles: the Account Executive signs the record · the Delivery Lead reviews it before Project Set-up is sent
Responsible roles: agency scope signatory · agency controller · Delivery Lead · Account Executive
Responsible roles: agency data owner · agency controller · Data Migration Lead · Delivery Lead
Responsible roles: agency project manager · optional agency subject-matter expert · Delivery Lead
Responsible roles: agency decision-maker · agency project manager · agency controller · Delivery Lead
Their team gets stretched twice — during discovery and scoping, and again during testing and training. Both times they are doing project work on top of their day jobs. Tell them at kickoff, because this is where projects slip.
Peak 1 — Discovery & scoping (Stages 4–5)
Peak 2 — Migration review, testing & training (Stages 7–9)